EICR Remedial Work: Repair an Unsatisfactory Report

Understand the next step after C1, C2 or FI observations. Arrange defined remedial work, keep the report and obtain the right completion records.

Short answer

An unsatisfactory EICR needs action on the observations, not just another summary page. C1 requires immediate action, C2 urgent remedial work and FI investigation without delay. For relevant private rentals in England, the usual 28-day remedial limit can be shortened by the report. C3 alone does not make the result unsatisfactory.

Send the complete report when asking for repairs

Include the observations, inspection schedules, test results, extent and limitations. A photograph of the satisfactory or unsatisfactory box is not enough to scope remedial work. The electrician needs to understand the identified defect, its location and what was excluded before deciding what further investigation or repair is appropriate.

Keep the original report even after work is completed. It records what was found at the inspection date and helps explain the follow-up. Do not discard the pages containing defects or describe a contractor's attendance as a satisfactory outcome without the relevant written confirmation.

Different codes require different next steps

C1 means danger is present and immediate action is needed. It must not be treated as permission to wait for the ordinary landlord deadline. C2 describes potential danger and calls for urgent remedial work. FI means further investigation is required without delay; the investigation can be necessary before the final repair scope is known.

C3 is an improvement recommendation. It is worth understanding the benefit, but a C3 observation on its own does not make the report unsatisfactory. Ask for the safety reasoning behind each proposal so optional improvements are not confused with the work needed to address dangerous observations.

Agree a defect-by-defect quotation

A useful proposal identifies what will be investigated, repaired, replaced or left isolated and how completion will be documented. Sometimes a targeted repair is enough; sometimes wider deterioration makes a partial or full rewire appropriate. A consumer-unit change is not automatically the answer to every unsatisfactory report.

Agree how findings outside the initial scope will be reported and authorised. Existing limitations may leave a question unresolved, so explain access constraints before the appointment. If tenants or a managing agent control access, coordinate that before treating a completion date as firm.

Keep the reporting duties alongside the repair

For private rentals in England, required remedial work or investigation normally has to be completed within 28 days, or sooner where specified. Report-sharing and completion-confirmation duties are separate from physically doing the work. Keep dated records and refer to the landlord guidance already linked on the site for the applicable documents and recipients.

At handover, ask the electrician to explain how the completed work addresses the observations and which certificates or written confirmation apply. An invoice alone is not a full technical record. Retain the report, completion evidence and records of later alterations together for tenants, future inspections or a sale.

When to call a professional

  • The report contains C1, C2 or FI observations.
  • Required work is outstanding or the deadline is approaching.
  • The proposed repair does not clearly match the report's findings.

For non-emergency work, call 07977 519533 or request a quotation. Do not wait for a form reply where there is immediate danger.

Services for the next step

Regional coverage

We discuss electrical work across Greenwich & Blackheath, Lewisham & Southwark, Bexley & Sidcup, Bromley & Beckenham, Dartford & Gravesend and Medway. Call to confirm availability for your location and job.

Frequently asked questions

Should I book a second EICR before any repair?

Start by understanding the complete existing report and required action. Inspection, further investigation and remedial work have different purposes; agree the appropriate scope rather than simply ordering another report.

Does every C2 item mean a full rewire?

No. The actual defect and installation condition determine the remedy. Ask for a reasoned proposal distinguishing targeted repairs from wider renewal.

Is C3 remedial work compulsory under the EICR result?

C3 recommends an improvement and does not by itself make the report unsatisfactory. Other property duties can still matter, so ask what the recommendation means in context.

Can a landlord wait 28 days with a C1 issue?

No. C1 requires immediate action. The ordinary rented-sector remedial deadline does not remove the need to address immediate danger or a shorter specified period.